MACE-DRAGADOS JV has received £826,103,802 from 1 department.
We currently have no contracts recorded for MACE-DRAGADOS JV.
A breakdown of the top government departments that have purchased goods and services from MACE-DRAGADOS JV, ordered by total spend.
£826 Million
A breakdown of the top government organisations that have purchased goods and services from MACE-DRAGADOS JV, ordered by total spend. These may be more granular than departments.
£826 Million
A breakdown of the top Expense Areas within each organisation that has purchased goods and services from MACE-DRAGADOS JV, ordered by total spend.
High Speed Two (HS2) Limited - £451 Million
High Speed Two (HS2) Limited - £107 Million
High Speed Two (HS2) Limited - £89 Million
High Speed Two (HS2) Limited - £86.4 Million
High Speed Two (HS2) Limited - £51.1 Million
A breakdown of the top Expense Types within each organisation that has purchased goods and services from MACE-DRAGADOS JV, ordered by total spend.
High Speed Two (HS2) Limited - £672 Million
High Speed Two (HS2) Limited - £81.4 Million
High Speed Two (HS2) Limited - £68.1 Million
High Speed Two (HS2) Limited - £3.43 Million
High Speed Two (HS2) Limited - £1.54 Million
| Date | Buyer | Amount | Expense Area | Expense Type | |||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| 2025-07-16 | £10,803,819 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-06-18 | £6,953,272 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-05-14 | £8,270,182 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-04-14 | £8,336,307 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-03-10 | £9,825,198 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-02-13 | £8,180,931 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2025-01-14 | £7,325,965 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-12-05 | £8,763,613 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-11-11 | £9,461,349 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-10-08 | £8,521,286 | AUC 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-09-06 | £12,104,197 | AUC 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-08-14 | £10,078,413 | AUC 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-07-08 | £11,240,054 | AUC 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-06-11 | £9,165,280 | AUC 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-04-17 | £16,014,587 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-03-11 | £12,965,085 | AUC - 000000 | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-02-07 | £11,634,534 | 000000 AUC | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2024-01-09 | £9,272,884 | 000000 AUC | AUC - Phase 1 | ||||||||
| Construction Partner - Euston Station (approved budget) | |||||||||||
| 2023-12-05 | £14,241,267 | 000000 AUC | AUC | ||||||||
| Construction Partner - Euston Station | |||||||||||
| 2023-11-08 | £10,734,633 | 000000 AUC | AUC | ||||||||
| Construction Partner - Euston Station | |||||||||||
Showing 1 to 20 of 63 transactions
The most recent payment data we have available for MACE-DRAGADOS JV is from July 2025. Government departments and public bodies typically publish their spending data on a monthly or quarterly basis.
MACE-DRAGADOS JV's government income has decreased over time. In 2025, they received £59,695,677, compared to £119,221,289 in 2024 - a decrease of 49.9%.
MACE-DRAGADOS JV has received a total of £826,103,802 from UK government organizations according to our records. This income comes from 1 government buyer.
The primary government buyer from MACE-DRAGADOS JV is Department for Transport, which has spent £826,103,803.